Run a small batch before the big one

A pilot run is 30 to 100 units built on the real line to find problems while they're cheap. What it must prove, and four things to have ready first.

In February 2026 we built our first panel-size PogoBot fixture at Insyght, for a customer's production line. Circuit boards leave the assembly machines several to a sheet, and that sheet is called a panel. The fixture presses spring-loaded pins onto the whole panel at once, so every board on it gets programmed and tested automatically, with nobody holding a probe.

Factory PCBA testing and label-printing setup.
Factory PCBA testing and label-printing setup.

It took four weeks. We're a small team in Delft, and a fixture like this is a product of its own, with a frame, electronics and software that all have to work before it's any use to a factory. Four weeks is a long time if you only start when the boards arrive.

That's the first half of this post: build the test before you need it. The second half is bigger. Before you pay for thousands of units, have the factory build a few dozen on the real line and watch what breaks.

So what should that small batch prove, and what do you need in your hands before it starts?

Why a good prototype isn't enough

Your prototype was built slowly, by an engineer who knows the product, from parts picked one at a time. If a connector didn't sit right, somebody nudged it and carried on. In production, operators who have never seen the product build it at speed, from parts that arrive by the thousand, and nobody nudges anything.

A pilot run (a small trial batch, 30 to 100 units, built on the real line with the real tools and the real operators) shows you what that change does to your product.

Don't wait for the factory to suggest it. A factory earns its money when your order ships, and nobody pays it to lower your risk. Most will ask for the deposit as soon as you approve a prototype, then start buying materials for the full order. Many line workers in China are also paid per piece, so a small batch that keeps stopping cuts their pay. Put the pilots in the contract, before the deposit.

Expect a low score. First pass yield is the share of units that pass every test the first time, with no rework. On a first pilot it's commonly only 10 to 30 percent, so most of the first units off the line will fail something.

First product off the line.
First product off the line.

What the test fixture does

Every unit has to be programmed and tested before it goes in a box. On an electronics line that's the job of a test fixture. The usual kind works with pogo pins, small spring-loaded pins that press onto test points (bare metal pads left on the board for exactly this) when the operator closes a lid.

Through those pins the fixture powers the board, loads the firmware (the software that runs on the device) and checks the voltages. It measures sleep current, the tiny current the device draws while it's idle, which decides how long the battery lasts. It tests the radio, writes a serial number, and saves the result under that serial number.

An operator with a multimeter can't do that a thousand times a day with the same care. A fixture can, and it leaves you a record of every unit. When a unit does fail in the pilot, an engineer still has to put probes on the board and work out why.

Probing the board, debugging the first units.
Probing the board, debugging the first units.

Get four things ready before the first pilot

A pilot only teaches you something if "good" was defined before it started, and if there's a reliable way to measure it. That takes four things.

Ready before the first pilotTESTEDTest fixtureBuilt and tried on realboards.SIGNEDGolden sampleOne for you, one for thefactory.IN YOUR HANDSParts listEvery part and everysupplier.WITH PHOTOSWork instructionsOne page per station.
Four things to have in hand before the first pilot starts.

The test fixture, built and tried on real boards. Start it the day the board layout is frozen, because it has its own lead time. Then feed it boards you know are good and boards you know are bad, and check that it tells them apart. If it's ready before the pilot, the pilot tests the tester too.

A signed golden sample. That's one approved unit, signed and dated, that defines what "pass" looks like. It doesn't have to be the best unit ever made. It should be a realistic one, with normal variation. You keep one and the factory keeps one, and every later argument about quality has something to point at. It helps to approve a limit sample next to it: the worst unit you'd still accept, such as one with the largest scratch you allow.

The parts list in your hands. The BOM (bill of materials) is the full list of every part in the product, with exact part numbers, suppliers, prices and lead times. If you don't hold it, a buyer at the factory can swap in a cheaper battery cell or plastic between batches and you'll hear about it from your customers.

Work instructions with photos, one page per station. The operator has your written instructions and nothing else, so a step that lives only in your head will be done differently on Tuesday. Show each step in a photo, with the tool it needs.

Give every pilot a question

Plan for more than one pilot. The first is often an engineering build of 1 to 30 units, still partly assembled the way a prototype is. Later ones use the final tools, the final operators and the final test stations, and you repeat them until the numbers hold.

Each run needs a written list of what you want to learn, one owner who understands the whole process, and a written report of problems and fixes afterward. The report sets up the next run. Across all the runs, five things have to be shown.

What a pilot run has to provePROOF 1RepeatabilityDo operators buildit the same wayevery time?PROOF 2YieldHow many unitspass every test thefirst time?PROOF 3ReliabilityDo units off thereal line survive thetests?PROOF 4ComplianceDoes theproduction unit stillpass?PROOF 5SupplyCan every part bebought at volume?
Five things the pilot runs must prove before you place the big order.

Repeatability means the product gets built the same way every time, across several batches. Yield is how many pass every test first time. Reliability means units from the real line survive your tests, since a hand-built prototype surviving them says little. Compliance means the production unit still passes, so ask your test lab what a late design or part change does to your certificates. Supply means every part can really be bought at volume.

Here's a made-up example of how yield moves. You build 50 units and 12 pass first time, which is 24 percent. You sort the 38 failures by cause. Say 20 failed programming because one fixture pin wasn't touching its pad, 11 had a battery connector that wasn't pushed fully home, and seven drew too much sleep current.

The first cause is the tester's fault and a quick fix. The second needs a photo of a properly seated connector in the work instruction. Only the third is a real product problem, and without sorting it would have stayed hidden among 31 other failures.

PilotBuiltPassed first timeFirst pass yield
1501224 percent
2504182 percent
3504896 percent

If the third result holds on another run with different operators, you have a process. If every unit still needs rework to pass, don't raise the order quantity yet. A bigger order from a broken process only produces more scrap.

Qualify parts before you buy thousands

Qualifying a part means checking two things. The supplier has to be able to make it the same way every time at your volume, and the part has to fit and work inside your real product. A part can pass the first check and fail the second.

One team ordered custom parts in production quantities after a single good prototype, hoping to save a month or two. The parts didn't fit the final design. It cost about $300,000 in scrapped parts, $200,000 in tooling and $50,000 in repeat testing, roughly $550,000 in total, plus seven months.

So start during prototyping. Order 3 to 10 pieces of each critical part, made the way the production ones will be, and test them in the product. Parts that take months to arrive can be ordered early, but only in small quantities, from a handful to a few dozen. Ask critical suppliers for their own scrap numbers too. A bad-part rate that goes 30 percent, then 10, then 50 tells you the supplier doesn't control the process.

Where it goes wrong

Treating the approved prototype as production ready. Teams that skip the pilot find the same problems at volume, with defect rates above 30 percent. When about 30 percent of parts need scrap or rework, expect the supplier to come back mid-project asking for something like 50 percent more money. Write at least two pilots into the contract. If a factory says a new custom product doesn't need one, I'd look for another factory.

Never getting the full parts list. One toy maker received gears in a cheaper plastic that stripped after about 20 hours of play. Without the supplier names you're also stuck with that factory, because requalifying a single custom part somewhere else can take up to six months. Have the contract give you the BOM and require your approval for any substitution.

Building the fixture last. The first pilot then gets tested by hand, the results depend on who held the probes, and you learn nothing about the tester. A fixture can take weeks to build, so starting late delays the pilot or wastes it. Start at layout freeze.

Selling the pilot units. Some of them have been opened and reworked. Ship them to impatient early customers and you get returns and bad reviews from the people who talk about you most. Label them and keep them for testing.