Blog · Production

Four places to catch a defect

Why a defect costs about ten times more at every stage it survives, the four checkpoints on a production line, and how checking 125 units judges 3,000.

In August 2026, first pass yield across the line held above 95 percent. First pass yield is the share of units that pass every test the first time, with no repair and no second try. So more than 95 of every 100 units needed no rework at all.

The credit for that goes to our engineer in Shenzhen, not to us in Delft.

Inspecting product on the factory floor.
Inspecting product on the factory floor.

I travel to Shenzhen regularly for production and sourcing, but a number like that is built step by step, by someone who is there. I learned how much that matters on my first wearable, the Shake-On bracelet. We had a lot of trouble with suppliers and the quality of their LiPo batteries (the flat rechargeable cells you find in most wearables), and I made plenty of mistakes there. My first trip to Shenzhen was to set up production of that bracelet, and standing on the factory floor is where I started to understand how things really get made.

You can't inspect quality into a product at the end. By then the money is already spent.

A defect gets about ten times more expensive at each stage it survives. It's far better to reject a bad batch of buttons on arrival than to find them inside 3,000 finished units. So this post is about where on the line you check, how the last check works, and what to do when a batch fails it.

Why you check four times

Take a snap-fit (a plastic hook that clicks two halves of a housing together) that's a little too weak. Spot it in the 3D design files and the fix takes minutes. Spot it on a prototype and you pay for another prototype round, about 10 times more. Spot it in production and you're changing a steel mold and reworking a batch. Out in the field you add returns and bad reviews on top.

That's the first reason not to rely on one big check at the end. The second is that an inspector there only sorts what has already been made. No inspector catches every bad unit, and nobody can see a latent defect (a flaw that only shows up after weeks of use).

So a line gets four checkpoints. When parts arrive, a sample is checked against the drawing while the rest is still in the box. During assembly, someone checks at the steps where mistakes happen most. At the end of the line, every unit is programmed and tested on a fixture (a jig that presses spring-loaded pins onto the circuit board and runs the tests automatically). Before shipment, an inspector checks a sample of the packed goods.

Four places to catch a problemA SAMPLEParts arriveCheck incoming partsagainst the drawing.AT KEY STEPSDuring assemblyCheck where mistakeshappen most.EVERY UNITEnd of the lineEach unit programmedand tested on a fixture.A SAMPLEBefore shipmentAn inspector checksabout 125 units out of3,000.
The four checkpoints on a production line. The earlier a problem is caught, the cheaper the fix.

How 125 units judge 3,000

Nobody opens all 3,000 boxes at that last checkpoint. The check uses sampling, and the rules for it are called AQL (acceptable quality limit, the worst defect rate you agree to tolerate). They come from an international standard with tables that say how many units to pull and how many defects to allow.

For a batch of 3,000, that's about 125 units. The inspector opens random cartons and checks each unit against your list and your approved sample.

Checking 125 units to judge 3,000Each dot is 5 units.Green: the 125 an inspector opens.THE BATCH PASSES WITH0critical defectsup to 7major defectsup to 10minor defects
A random sample of 125 units stands in for the whole batch of 3,000.

Defects come in three classes. A critical defect is unsafe or against the law, like a swollen battery or a sharp edge. A major one means the customer would send it back: it doesn't power on, or it won't pair. A minor one is something the customer would live with, like a light scratch on the underside.

With the limits most buyers start from, the batch passes with no critical defects, up to 7 major and up to 10 minor in those 125. An eighth major defect fails the whole batch, and so does a single critical one. A failed batch stays at the factory until it's sorted.

The sample grows more slowly than the batch (about 200 units for a batch of 8,000), and a batch that passes still contains some defects. Sampling also never replaces the test at the end of the line. Every board gets tested there, and the sample covers the rest: looks, assembly, labels and packaging.

Write down what "good" means

You can't hold a factory to a standard you never defined. Leave "acceptable" open, and the argument ends with "our other customers accept this".

Start with a golden sample (a finished unit that you and the factory both sign, with one kept on each side). Add a spec sheet: dimensions with tolerances (how far a measurement may be off), weight, material, color and finish, label text and packaging. One buyer approved a cooking pot by sample and received pots 15 to 20 percent lighter, because nothing on paper said the metal couldn't be made thinner.

Then write your defect list in the three classes, with a photo for each. For a fit that's hard to judge by hand, such as how firmly a clip holds, a simple checking fixture costs roughly $300 to $400 and turns an opinion into a pass or a fail.

Have the sheet translated and signed by the factory, and attach it to your contract. Say in writing that the standard doesn't move with the price. Many factories assume that if you pushed hard on price, you accepted lower quality in return.

Match the checks to the risk

Start with one question. Has this exact factory made this exact product, at volume, for a market like yours? If yes, and a defect rate of 2 to 3 percent wouldn't hurt you, the check before shipment is enough. If the product is new to the factory in any way, inspect three times.

CheckWhenWhat it catches
First unitsFirst finished units off the lineSetup, tooling and assembly mistakes
Mid-run10 to 30 percent of the batch doneThe real defect rate, while rework is cheap
Before shipmentAll finished, 80 percent packedQuantity, labels, looks, function

Do that last inspection at the factory and not in a shipping warehouse, so the people who built the units see the findings the same day. And keep the final payment behind the result, because once you've paid in full, nothing forces a rework.

Ask for first pass yield at every station

Here's a worked example with made-up numbers. Say 1,000 boards go into the functional test (the station that checks each board really works) and 940 pass straight away. First pass yield is 94 percent. Of the other 60, say 50 get repaired and pass on the second try. The factory reports a final yield of 99 percent, which hides all that rework. First pass yield shows it.

It also multiplies along the line. Five test stations that each pass 98 percent first time sound excellent. Together they let only about 90 percent of units through untouched, so one unit in ten needs rework somewhere.

Small losses add up along the lineSTATION 198%STATION 298%STATION 398%STATION 498%STATION 598%PASS ALL FIVE90%Each station passes 98 of every 100 units the first time. One in ten still needs rework somewhere.
Five stations at 98 percent each leave only 90 percent of units passing all five untouched.

Ask for the number per station, per day, with the top three reasons for failing. When it drops, something changed: a new reel of parts, a worn fixture, a new operator. Somebody has to walk to that station the same day and look. That's hard to do from Delft, which is why the credit for our August number goes to our engineer in Shenzhen.

Visiting our team in Shenzhen and Hong Kong — east–west collaboration is everything.
Visiting our team in Shenzhen and Hong Kong — east–west collaboration is everything.

Number every unit, and plan for a failed batch

Give every unit a serial number that links it to the batches of parts inside it. When one bad batch of batteries gets into production, you want to recall the 800 units that got those cells and leave the other 39,200 alone. Samsung's Galaxy Note 7 had batteries from two suppliers, and only one supplier's cells caught fire. It still cost Samsung more than $5.3 billion.

A connected product gets most of this for free. Every device already has a unique ID, and the test fixture can log it with the date, the firmware version and the test result. Build it in from the first run, because you can't add it afterward. Test it with a mock recall: pick one batch of parts and see how fast the factory can list the units it went into.

When an inspection does fail, stop first. Tell the factory in writing that nothing ships until you release it. Collect photos with a ruler in frame, and check your own spec sheet before you blame anyone. Then ask for the cause in writing, and decide together whether the batch gets reworked or remade.

Where it goes wrong

Approving a sample and writing nothing down. A sample can't show tolerances or packaging, and the people who remember the agreement change jobs. Anything you leave unspecified gets made the cheapest way. Avoid it with a signed spec sheet, attached to the contract.

Calling a box count an incoming inspection. A count would never catch the factory that fitted 16 GB memory chips sold as 64 GB. Ask what's really checked, and whether the findings go back to the part supplier. A supplier who never hears about 2 percent scratched parts sends 10 percent next time.

Accepting "operator error, retrained" as a cause. If one untrained person could ruin a batch, the process allowed it. Ask how the fix got into the work instructions and the fixtures. I'd also ask whether the new method is slower than the old one, because a slower fix gets dropped the first time the schedule is tight.