In May 2026, data from MedeMeter went live in Samen Meten, the citizen-science measurement network of RIVM, the Dutch national institute for public health. MedeMeter is a solar-powered sensor for air quality and noise that we built at Insyght, in Delft.
Nobody looking at that data cares how production went. The sensors have to keep measuring, month after month.
I learned early that this part is hard. At Shake-On, my first wearable, we had a lot of trouble with suppliers and the quality of their LiPo (lithium polymer) batteries, and I made plenty of mistakes there. At Xeelas, the units we shipped went onto diesel generators and fuel tanks across Europe, and onto tank containers that sit on a ship for weeks. A product's real life starts after the factory, and so does a lot of the work.

Most founders treat the first shipment as the finish line. For the factory, it's the moment the attention drops. The engineers who watched over your trial batch move on to the next customer, and your order becomes one line on the planner's list.
This post is about what comes next: keeping batch 10 as good as batch one, and getting it to your customer in one piece.
Why batch one is the best one
The factory builds your first batch carefully because it expects you to look. If nobody complains, batch two gets trimmed a little. Batch three, a little more. The supplier never asks, because asking invites a no.
This slow decline has a name: quality fade. Paul Midler, who wrote Poorly Made in China, described it in 2007. In his original case, steel bars ended up about 10 percent lighter than the spec. In a connected product, the things that fade are hidden inside: a battery cell with less capacity, thinner plating on the contacts, a cheaper capacitor. The unit looks the same and passes a quick function test.
The reason is money. On a product with a 5 to 10 percent margin, swapping a branded part for a fake in about one unit in 10 can roughly double the factory's profit. It's never every unit, because a cluster of failures would give it away.
A typical order from Asia takes about 80 days from purchase order to your warehouse, most of it waiting for parts, a slot on the line, a ship and customs. Sending defective goods back is close to impossible. So a bad batch you discover at home costs you the batch plus another 80 days.
Keep looking after the good batches
Give batches 3, 5 and 10 the same inspection as batch one, and check the parts as well as the function. Every so often, open a few units from a new batch. Weigh them, measure them and run a battery capacity test, then compare with the golden sample (the approved reference unit that you and the factory each keep). Don't announce which batch you'll open.
Pick the samples and the test lab yourself. A supplier who picks both can send 10 samples and show you the one that passed. And show up, with your own people or an inspection firm. At Insyght we have an engineer based in Shenzhen, which makes that part easy for us.
Then put changes in writing. Your purchase order should say that no part, material, process or firmware version changes without your signed approval. The usual tool is an engineering change request (a one-page form describing the change, which you sign before it happens).
A small buyer, with orders of $10,000 to $50,000, can't dictate prices. You can get a named production site, written change approval and an honest lead time (how long an order really takes). Ask before the first order, while you still have something the supplier wants.
Fix problems in loops
Check your own side first. The standard has to be written down, and the complaint has to rest on a proper sample from several cartons. Two bad units from one box prove nothing.
Then work on one defect at a time. Pick the top defect and find the cause with data. Change one thing, so you know what worked. Measure again. If it helped, make it the standard.
Take a made-up example. Batch four is 2,000 units and 90 fail the final test, which is 4.5 percent. Sorted by cause, 50 have a battery connector that isn't pushed fully home, 25 have a scratched lens and 15 are a mix. Plan: the connector is the top defect, and watching the line shows that operators can't feel when it clicks. Do: one change, a small holder that only closes when the connector is seated. Check: batch five, also 2,000 units, has six connector failures instead of 50. Act: the holder goes into the work instruction and every operator is trained on it. Now the scratched lens is the top defect, and the next round starts.
Expect 10 to 20 rounds per type of problem, and 6 to 12 months before a fix really sticks.
Pack for the whole trip
The day your first boxes leave the factory is a proud one. It's also the last day anyone handles them carefully.

The layer that does most of the protecting is the master export carton (the big brown box that holds many retail boxes). It gets stacked five high, dropped off a truck bed and squeezed for weeks. If you say nothing, you get the factory's default, which is built to reach the freight company and no further. So write your own spec: board grade, units per carton, cartons per pallet, and the test it has to pass.
The test to ask for is ISTA 2A, a standard transport test that costs about $600 to $1,500. A lab puts a full carton through six steps in a fixed order: two rounds in a climate chamber, a press that copies weeks of stacking, vibration that copies a truck ride, drops from 0.5 to 1.5 meters, and vibration again. That second round exists to expose what the drops broke quietly.
Then there's the container. Sea freight means six to eight weeks in a steel box that heats up by day and cools at night. Water condenses on the roof and drips onto your cartons, and damp cardboard goes soft. Keep packing and storage under 60 percent relative humidity. Past 70 percent, mold can start on cardboard and labels. Hang drying strips high in the container. A set for one container costs around $50.
Shipping terms and customs
Shipping terms settle who pays for which part of the trip, and when the risk of loss moves from the seller to you. Nearly every Chinese quote says FOB (Free On Board), where the risk becomes yours once the goods are loaded onto the ship.
The trouble is the stretch before that. You typically pay the balance before the goods leave the factory. Then they ride a truck to the port and wait for a ship, sometimes for weeks. Under FOB that stretch is the supplier's risk, and suppliers almost never insure it. The 2015 explosion at the port of Tianjin destroyed about 8,000 new cars waiting for shipment.
With FCA (Free Carrier), the risk moves when the goods are handed to your carrier, at a place you put in writing: the factory gate or the port. Your own cargo insurance covers everything from there. It can cost a little more. For a container of electronics, I'd pay it.
Customs lands on you as well. Every product has an HS code (the number customs uses to set the duty rate), and your supplier will suggest the one that worked for their last customer. The legal responsibility sits with the importer, and that's you, for both the code and the country of origin. One company shipping gift boxes paid about $5,000 in duty it hadn't planned for on $20,000 of goods. Have a customs broker check the code and the origin before the first shipment.
Where it goes wrong
Relaxing after one good batch. Inspections stop, the fade starts, and you hear about it from customers, with the fix 80 days away. Keep inspecting, and open up units from later batches.
Agreeing changes in chat. The chat app belongs to the salesperson, and the company keeps no record of it. Six months later nobody knows what was agreed, and you pay for the rework. Confirm it by email the same day, and use the signed change form.
Shipping a failed batch "just this once". Without paper, that batch is the new standard. If the deadline forces your hand, have the supplier sign that it was an exception. Don't accept a discount on the next order instead, because the supplier earns it back by cutting corners.
Testing the box with dummy loads. Empty boxes or sandbags don't put the same weight in the same places. The report says pass, and the damage shows up later across a whole shipment. Use real units in real retail boxes, and run the full sequence in order.
Asking for your files and molds on the day you want to leave. A careful move to another factory takes two to six months, and a supplier who senses it has good reason to hold things back. Expect a "release fee" of 15 to 30 percent on top of what you paid for the molds. Build the exit package from the first order: design files, the full parts list, golden samples, and a written right to collect your molds.