Toyota Material Handling needed a new remote control for its order-picker trucks, the trucks warehouse workers use to collect the items for an order from the shelves. Toyota wanted it to keep up with competitors, and the existing remote was clunky. I'd started at Inspiro in 2014 as an embedded engineer, and I got to build the new one.
The wish list was hard to combine. It had to be very small. It also needed Bluetooth, an NFC reader and wireless charging inside, in a housing tough enough for a warehouse. And it was a safety control, so it had to work every time.
So I built one, and then another. I rapid-prototyped solution after solution until the form factor was right. It ended up as something you wear: a stop control in place of a clunky remote.

None of those early builds was the product. Each one was there to answer a question about size, safety or toughness.
That's what a prototype is for. It's an experiment that answers one question. The trouble starts when one prototype has to impress an investor, prove the radio range, survive a drop and show the final color. It does all four badly.
This post is about picking the question, picking the cheapest build that answers it, and knowing when to stop changing the design.
What a prototype can and can't tell you
Three questions come up again and again. Fit: does it physically do the job? Form: how does it look and feel? Function: does it perform, and does the user understand it?
A fit prototype can be switches in a cardboard box. A form prototype can be an empty shell, sanded and painted. A function prototype is ugly, with wires hanging out, but it measures, connects and runs on its battery.
What no prototype tells you is whether a factory can make it. You built it yourself, by hand. You took parts from a drawer, made a cable to length and filed one edge until the lid closed. An operator on a production line has your written instructions and nothing else.

That's why a prototype that works is roughly 70 to 80 percent of the design work. On the way to the factory, parts bought in volume come from other batches, the rough firmware gets cleaned up and picks up new bugs, and nobody files anything by hand anymore.
How prototype parts get made
A 3D printer builds the part in thin layers, so the part is a stack and it's weakest between the layers. A printed snap-fit (a small hook that clicks two halves together) can break even when the design is fine. In CNC machining, a computer-controlled cutter carves the part from a solid block of the real plastic or metal. You get strength and tight fits, and you pay per part.
Vacuum casting starts from one master part, printed and polished by hand. Silicone rubber is poured around it to form a mold, and liquid resin is drawn into that mold under vacuum, so no air bubbles get trapped. The soft silicone copies every detail and wears out after about 5 to 20 parts.
The last step before production is a soft steel mold: a real injection mold, cut from steel that hasn't been hardened, so it's faster to machine and wears out sooner.
A shape that prints fine can be impossible to mold. A mold needs draft angles (slightly sloped walls) so the cooled part can slide out of the steel. If your product will be molded, design for molding from the first serious CAD model. Otherwise you redesign later, and the tests you ran on the old shape no longer count.
Write the question down first
Before you build anything, write one sentence: the question this build has to answer. Then pick the cheapest way to answer it.
If you want to know how it sits in the hand, print it. If you're testing a clip that has to bend again and again, machine it from the real plastic. A brittle printed resin will snap and tell you nothing about your design. If you need the final color and finish for a customer demo, cast it.
For a new idea, the first question is whether it works at all. Answer that with a dev board (a ready-made circuit board from the chip maker, meant for experiments) and a sensor wired to it. A custom circuit board and a mold for a concept you've never seen work usually end in expensive rework.
Plan the four builds
Electronics companies split the work between prototype and production into named builds, and every serious factory knows the names. Each build is a small batch made to answer one question.
After the proof of concept comes EVT (engineering validation test). It's the first build that looks like a product, with a custom circuit board. You check it against the specs: radio range, battery life, sensor accuracy, charging.
DVT (design validation test) takes the final design and tries to break it with drops, heat, water and aging. Base the tests on the worst use you'd still call normal. A phone that slides off a coffee table, about half a meter onto a hard floor, has to survive. A two-meter fall is abuse, and you're allowed to decide that on purpose.
Then the molds and test fixtures are made. PVT (production validation test) asks whether the real line can build good units again and again. Volume goes up slowly on purpose, so a problem shows up at 200 units and not at 20,000.
Put all four on a calendar, each with what has to be true to pass.
Freeze the design after DVT
A design freeze means that from one date on, nothing changes without a written change request that somebody reviews and approves. It sounds like paperwork. It's the cheapest protection you'll ever buy, because everything after this point is cut in steel.
A flaw you catch while writing requirements costs minutes. In CAD it costs hours or days. Once the mold exists, it costs a new mold. Tooling scrapped or reworked over a late change typically runs from about $30,000 to $200,000.
Here's a made-up example. Your housing needs two molds, quoted at $40,000 together. There's a trade fair in 10 weeks, so you order the molds while the last design round is still being tested. That saves 3 weeks. Then the drop test cracks the housing, and the fix makes it 3 mm longer. A steel mold can't be stretched. You pay the $40,000 again and wait another 6 to 8 weeks.
So don't order a tool until the final design has been built and tested as a working prototype. And when you freeze, write down exactly what you tested: which version of the parts list, which firmware release, which suppliers. Your test results count for that combination only.
Put it together one piece at a time
Each part can pass on the bench and the product can still fail. There, the board runs from a lab power supply with open air around it. Inside the housing it sits next to a battery, an antenna and a warm charging circuit. Heat has nowhere to go, and parts that sit close together start to disturb each other. One engineering team ended up adding a fan just 10 mm across to cool a product that had run fine in the open.
So test each subsystem alone first, then add them to the full build one at a time. When something breaks, you'll know which addition did it.
Then use it the way a user would, in the place where it'll be used. A handle at 58 to 60°C can sit inside the limit of a safety standard, and a person will still drop it.

Where it goes wrong
Treating printed parts as if they were molded. Snap-fits, hinges and drop behavior all differ, so a passed test can mean nothing and you lose a test round. Anything you test until it breaks should be made in the production material.
Skipping the tolerance math. Every part is made within a tolerance, a permitted range around its intended size. As an example, say the opening in the lid is 60.0 mm and the base that goes into it is 59.8 mm, each give or take 0.15 mm. A lid at 59.85 mm won't go over a base at 59.95 mm, although both parts pass inspection. It's not unusual for around 30 percent of a first production batch of housings to need rework for this reason. Do the sum for every set of parts that fit together, before the molds are ordered.
A "drop-in" replacement part. In one documented case, a chip was swapped for a cheaper one with the same inputs and outputs on paper. Re-running the old tests turned up subtle differences, and production slipped by 10 months. Any swap gets the full test plan again.
Nobody from outside looks at the design. Founders skip the review because the idea feels too secret to show, and then spend more on patent lawyers for a product that has never been proven to work. I'd turn that around. Have an experienced engineer from outside the project try to break the design on paper before the freeze. It takes a few days.